Oct 26, 2009 04:37 PM in Energy & Sustainability | 4 comments
First light! Panels start producing power, but paperwork drags on
Editor's Note: Scientific American 's George Musser will be chronicling his experiences installing solar panels in Solar at Home (formerly 60-Second Solar). Read his introduction here and see all posts here.
What a beautiful Indian summer day to inaugurate our solar panels. The electrician finished wiring up the inverter on Saturday and flipped the switch, and I spent much of yesterday running to the basement and checking the inverter readout to confirm that the sun was indeed powering our house. The system isn’t hooked up to the grid yet, but at least we're offsetting some of our domestic power consumption.
I found that the array generated power almost all day, from 8 a.m. to 6 p.m. At first it was just a trickle, but it reached a maximum of 1,995 watts around noon (at our longitude, the sun reaches its highest elevation at about 12:40 p.m. Daylight Savings Time). In all, the array put out about 9.5 kilowatt-hours of energy yesterday.
What a relief. After the problems we’ve had with our contractor, I half-expected the system to fail in a blaze of sparks. In the event, it produced just what the PV Watts calculator predicted. The system is rated at 3 kilowatts of DC power, and at this time of year, the sun’s rays strike the panels at an angle of about 45 degrees, which cuts the output by about a third.
Much as I savored the moment, the process isn’t over yet. The following still needs to happen:
- The town building department needs to inspect the electrical and structural work.
- The utility needs to install a new electric meter.
- The state needs to inspect the system.
- The utility needs to visit to close the loan that constitutes the largest chunk of the subsidy. Several people commenting on my earlier blog posts said that solar paperwork isn’t as bad as I made it out to be, but I don’t think they were aware of the complications of this particular loan program. Despite the difficulty, I’m grateful to the utility for providing oversight of our installer.
The bottom line is that I don't think solar isn’t ready for prime time yet. If your state doesn’t have a company that offers leasing or power-purchase agreement, whereby they handle all the nitty-gritty for you, I’d hold off a couple of years until the government agencies, utilities, and installers work out the kinks.
1st Light Energy contractor installing the inverter in George's basement
You Might Also Like
Discuss This Article
Subscription Center
Most Popular Blog Posts
9,000-year-old brew hitting the shelves this summer
New solar-cell efficiency record set
AIDS vaccine surprises scientists, proves partially successful
Is birth control the answer to environmental ills?
Editor's Pick
-
Adapting to the Freshwater CrisisForward-thinking experts are getting a better handle on the growing global water shortage and coming up with innovative approaches to ensuring the security, safety and sustainability of this resource
Energy & Sustainability Newsletter
Get weekly coverage delivered to your inboxPodcasts
-
60-Second Earth
RSS ·
iTunes
The Jellyfish Menace
click to enable
-
60-Second Science
RSS ·
iTunes
Plants Share Light If Neighbor Is Related
click to enable
Slideshows
How Long Can a Nuclear Reactor Last?
Growing Skyscrapers: The Rise of Vertical Farms
Will solar thermal heat up again?
New solar-cell efficiency record set
Powering a Green Planet: Sustainable Energy, Made Interactive
Fight to protect California condors from lead ammunition moves to Arizona
Circulation of LHC Beams Could Resume in Earnest over the Weekend
Measuring Up: New NIST Director, Plus Big Budget Put Measurement Science in Public Eye
How Long Can a Nuclear Reactor Last?
What to Do About Endocrine Disruptors? A Q&A with Linda Birnbaum